How to Perform a CPM Schedule Health Check: 25-Point Checklist

By the P6 Project Controls Team | PMP®, PMI-SP®, PSP®, CMIT®

Why Schedule Health Checks Matter

A CPM schedule is only as valuable as its accuracy and integrity. A schedule riddled with logic gaps, artificial constraints, and unrealistic durations is not just unreliable — it is a liability. It cannot accurately predict completion dates, it undermines delay analysis, and it erodes stakeholder confidence.

Regular schedule health checks are essential for maintaining a schedule that serves as a genuine project management tool rather than a contractual formality.

Schedule Health Check Dashboard — 25-Point Assessment

The 25-Point Schedule Health Check

Logic Integrity (Points 1-6)

1No Open Ends: Every activity has at least one predecessor and one successor (except project start/finish milestones).
2Relationship Types: FS relationships dominate. SS, FF, and SF relationships are justified and documented.
3No Negative Lag: Negative lag (leads) should not exist. Use SS relationships with positive lag instead.
4Reasonable Lag Values: Lag values are realistic and documented. Excessive lag often masks missing activities.
5Logic Density: Average relationships per activity should be between 2.0 and 2.5.
6No Redundant Logic: Remove relationships that are already implied through transitive logic.

Critical Path Analysis (Points 7-10)

7Critical Path Continuity: The critical path runs logically from project start through construction activities to completion.
8Critical Path Length Index (CPLI): Should be close to 1.0. Values below 0.9 indicate the critical path may be unrealistic.
9Near-Critical Activities: Identify activities with total float between 1-20 days that could become critical.
10No Negative Float: Negative float indicates scheduling conflicts that must be resolved.

Duration Analysis (Points 11-15)

11Duration Reasonableness: Activity durations reflect realistic production rates based on scope quantities.
12No Excessive Durations: Activities longer than 44 working days should be subdivided by area, phase, or scope.
13Baseline Execution Index (BEI): Completed activities should have actual durations close to their original durations.
14Remaining Duration Accuracy: In-progress activities have remaining durations that reflect current field conditions.
15Calendar Assignments: Activities are assigned appropriate calendars (5-day, 6-day, 7-day, weather-adjusted).

Constraints & Coding (Points 16-20)

16Minimal Hard Constraints: Less than 5% of activities should have hard constraints (Must Start/Finish).
17Complete Activity Coding: All activities are coded per contract specifications (area, phase, trade, responsibility).
18WBS Structure: Logical and consistent Work Breakdown Structure aligned with the project scope.
19Milestone Completeness: All contract milestones are present with correct dates.
20Activity ID Convention: IDs follow a logical, sortable convention.

Performance & Compliance (Points 21-25)

21Resource/Cost Loading: Schedule is properly loaded per contract requirements.
22Out-of-Sequence Progress: Identify and resolve any activities progressing out of logical sequence.
23Actual Start/Finish Dates: Completed activities have accurate actual dates recorded.
24Total Float Distribution: A healthy float distribution — not too much concentrated float or too little.
25Specification Compliance: Schedule meets all contract scheduling specification requirements.
Download Our Free Checklist: Visit our interactive Schedule Health Check tool to get an instant score for your project schedule across all 12 key categories.